Wednesday, October 7, 2009

Grand Coulee Dam’s control system

The U.S. Army Corps of Engineers has selected RTI Data Distribution Service for an upgrade of the Grand Coulee Dam’s control system. RTI’s middleware will integrate components of the dam’s next-generation Supervisory Control and Data Acquisition (SCADA) system, enabling more efficient and reliable hydroelectric power generation. The Grand Coulee Dam is the largest hydropower plant in the United States. The project to retrofit the control system is for the U.S. Bureau of Reclamation (BOR) in cooperation with the Bonneville Power Administration (BPA). The U.S. Army Corps of Engineers Hydroelectric Design Center (HDC) is the system integrator; HDC selected RTI Data Distribution Service to implement a highly available, high-performance and scalable control system. (Dave Brown, the project manager and system architect for the U.S. Army Corps of Engineers.)

No comments: